Open topic with navigation
Setting Up the Maxwell Management Suite Bid
When you are ready to export your information to Management
Suite, go to Summary and select New Acct
Bid from the Open Summary window.
Note: If
the New Acct Bid button is not
visible, make sure you have configured Estimating correctly using the
General Options.
The Properties window for the Bid Export Report will
display.
This window has several tabs with settings for the
Bid Export Report.
Template
Tab
The Template tab allows you to save Bid Export
Report setting configurations that can then be selected for future
Bid Export Reports involving the loaded Estimate.
ADD: Adds
a setting template to the window. When a saved template is highlighted,
the settings of the Properties window are changed to how they were
configured when the template was added. In addition, any selected
Default Items will be added into the Bid Export Report.
COPY: Use
the Copy feature to copy the selected bid export template within the
current bid or to copy the bid export template to another data set
or another estimate. Follow the prompts on the Open Summary window
to select where you want to copy the bid export template to: Data
Set or Estimate.
Note: Remember to rename your copy to a descriptive name that suits
your needs.
RENAME:
Allows you to rename the selected template.
DELETE:
Deletes the selected template.
Note: Templates
for Bid Export Reports can also be configured by going to Data > Data File Maintenance
> Bid Export Templates or Estimate
> Estimate File Maintenance > Bid Export Templates. Templates
created through Data File Maintenance will be available for all new
Estimates, while those created through Estimate File Maintenance will
only be available for the Estimate being modified.
When accessed through the above methods, the Template
tab will feature an additional button: View Default Items.
VIEW DEFAULT ITEMS:
This option will open an empty Bid Export Report screen. You
can then takeoff default items which are added to the report when
it is run. The Default Items screen functions just like a regular
Bid Export Report. However, you cannot actually create a bid file.
General Tab
The General tab contains general settings for the
Bid Export Report.
NAME: By
default, this field is set to the name of the Job. It can be
modified if desired.
REPORT DESCRIPTION:
A brief description of the Bid Export Report. If a template
is selected, its name will be automatically entered into the field.
COMMENT:
Comments on the Bid Export Report can be entered in this field.
LABOR BURDEN %
/ LABOR RATE / TAX %: Enter in the values for these
settings in the provided fields.
CHANGE ORDER ID:
This field can hold a three-character string. If this
field is filled in, the XML file generated for Estimating will include
the ID information, allowing it to be imported into Management Suite
as a Change Order.
Profit & Overhead Tab
In the Overhead %
and in the Profit % columns, select “Per Cost Type” or “Overall.”
INCLUDES OVERHEAD:
This option will allow profit to be drawn from overhead during
calculations for the Bid Export Report.
Note: If
this option is selected, you will have to also select the same option
in your Management Suite program for it to apply correctly.
PER COST TYPE:
In this area, you can set the Overhead or Profit percentage
for individual item types that are in the Bid Export Report.
OVERALL:
This setting allows the user to set an Overall % for Overhead
or Profit for all item types.
USE LABOR PERCENTAGES
FOR ALL LABOR VALUES: If this box is checked, the Labor
overhead and profit will be applied to all labor values, regardless
of their cost type.
Divisions
Tab
In the
Divisions tab, you can specify
overrides for the segments used in Bid Exports for Field labor cost
type items.
NOTE: To effectively
use this feature, you must have “Create Separate Material and Labor
Items” checked in the Accounting Integration section of your Summary
Preferences. If this box not checked, items that contain both
Material and Labor values will appear as Cost Type “Material” and
your overrides selected here will not be applied.
Check
the box next to Use Field Labor Overrides. Then use the drop down
arrow next to each Segment field to select the segments you want used
in the report.
The Segment
1, 2 and 3 entries correspond to the segments selected in the
General Options Accounting Integration
tab.
General Notes Tab
This tab provides a place to store notes regarding
the Bid Export Report.
Include Tab
This tab allows you to specify which Takeoff Sections
you want included in the Bid export file. To select/deselect
a Section, click on the box by the Section’s name. By default, all
Sections are initially selected. In addition, you can use Select
All to quickly select all the available Sections.
You can also filter what is included in the report
by any of the six user-defined levels or by Sections. To do so, use
the drop-down menu beside Include
the following checked. You can also use Show
Entries to display the number of items in any particular Section
or user-defined level filtered.
Once you are finished setting-up the Bid Export Report
options, use one of the following options:
RUN: Will run,
and then open, the Bid Export Report with the current settings.
CANCEL: Cancels
the Bid Export Report setup.
SAVE TEMPLATE:
If a Template is selected, using this button will save/update the
settings stored in the entry.
Note: Many
of these Properties can be adjusted within the Bid Export Report by using
the Edit
> Reallocate Profit and Overhead menu option.
© 2016 Viewpoint, Inc.
Construction Specific Software that Integrates
www.viewpoint.com
For support on the Web (and Online Support Chat), visit
ClearView.