Setting Up the American Contractor Bid
After entering Summary, click New
AC Bid, located at the bottom of the Open Summary window.
The Properties window for the American Contractor Bid
will display.
This window has several tabs with settings for the
American Contractor Bid.
Template Tab
The Templates tab allows you to save AC Bid setting
configurations that can then be selected for future AC Bids involving
the loaded Job.
Add: Use
the Copy feature to copy the selected bid export template within the
current bid or to copy the bid export template to another data set
or another estimate. Follow the prompts on the Open Summary window
to select where you want to copy the bid export template to: Data
Set or Estimate.
Note: Remember to rename your copy to a descriptive name that suits
your needs.
Copy: Creates
a copy of the selected setting template.
Rename:
Allows you to rename the selected template.
Delete:
Deletes the selected setting template.
General Tab
The General tab contains general settings for the
American Contractor Bid.
NAME: By
default, this field is set to the name of the Job. It can be
modified if desired.
REPORT DESCRIPTION:
A brief description of the American Contractor Bid. If
a settings template is selected, its name will be automatically placed
in the field.
COMMENT:
Comments on the American Contractor Bid can be entered in this
field.
LABOR BURDEN %/LABOR
RATE / TAX Buy %/: Enter the values for these settings
in the provided fields.
LABOR TAXED WHEN
SOLD?/MATERIAL TAXED WHEN BUYING?/NON-LABOR TAXED WHEN SOLD?:
If any of these conditions are true in your American Contractor
Bid, click on the corresponding box to activate the condition.
BASE REPORT: If this American Contractor Bid is a
Change Order, select the American Contractor Bid to which the Change
Order refers.
CHANGE ORDER ID:
Every Change Order must have an ID number. Enter the desired
ID number in this field.
Profit & Overhead Tab
The Profit and Overhead tab establishes settings
either Per Bid or Per Item, depending on which one you select. Per
Bid allows you to set variables that affect the American Contractor
Bid as a whole. Conversely, the Per Item is used to apply settings
to individual item types.
OVERHEAD AMOUNT/PROFIT
AMOUNT: To set these amounts for the American Contractor
Bid, fill in the appropriate fields.
In the Overhead % and in the Profit % columns,
select “Per Cost Type” or “Overall.”
INCLUDES OVERHEAD: Check this option to allow profit to
be drawn from overhead during calculations for the American Contractor
Bid.
PER COST TYPE:
In this column, you can set the Overhead or Profit percentage for
individual cost types that are in the American Contractor Bid.
Use Labor Percentages
for all Labor Values: Check
this option to apply the percentages set to all Labor Items instead
of per Cost Type.
OVERALL:
This setting allows you to set an Overall % for Overhead or Profit
for all cost types.
Divisions
Tab
In the
Divisions tab, you can specify
overrides for the Area, Activity and Group used in Bid Exports for
Field Labor cost type items.
NOTE: To effectively
use this feature, you must have “Create Separate Material and Labor
Items” checked in the Accounting Integration section of your Summary
Preferences. If this box not checked, items that contain both
Material and Labor values will appear as Cost Type “Material” and
your overrides selected here will not be applied.
Check
the box next to Use Field Labor Overrides.
Then use the drop down arrow next to each field to select the area,
activity and group you want used in the report.
The Area, Activity
and Group entries correspond to those selected in the General
Options Accounting Integration
tab.
General Notes/Specification Notes/Note
for Customer/Notes for Vendor Tabs
These tabs allow the user to enter various types
of notes regarding the American Contractor Bid.
Include Tab
This tab allows you to specify which Takeoff Sections
you would like to be included in the American Contractor Bid. To select/deselect
a Section, click on the box by the Section’s name. By default, all
Sections are initially selected. In addition, you can use Select
All to quickly select all the available Sections.
You can also filter what is included in the report
by any of the six user-defined levels or by Sections. To do so, use
the drop-down menu beside Include
the following checked. You can also use Show
Entries to display the number of items in any particular Section
or user-defined level filtered.

Once you are finished setting-up the American Contractor
Bid summary, use one of the following options:
RUN: Will run, and then open, the American Contractor Bid summary
with the current settings.
CANCEL: Cancels the American Contractor Bid Summary.
SAVE TEMPLATE: If a Template is selected, using this option
will update the settings stored in the entry.
Note: Many
of these Properties can be set within the American Contractor Bid Summary
by using the Edit > Reallocate Profit and
Overhead menu option.